Around 30 labourers were reportedly inside when the structure gave way.Initial findings indicated that the building had been approved for a basement, ground floor and one additional storey, but six extra floors had allegedly been constructed.
Police detained six people in connection with the case, including the contractor and the structural engineer, while the SBCA suspended six officials.According to a Rescue 1122 (Sindh) spokesperson, the 15th victim was identified as Muhammad Mufeed, son of Ghamin Gul, while the identification process for the other recovered body was underway.The latest recovery followed the retrieval of five bodies on Saturday, which had taken the death toll to 13.
The rescue operation continued for a fifth day as teams searched the debris for people feared trapped beneath the collapsed structure.Rescuers pulled one person out alive using modern equipment to detect signs of people trapped beneath the debris in one section of the building on Friday.
They then reached an “unstable portion” of the collapsed structure and managed to pull out the construction worker alive.Read: Deadly building collapse FIR leaves officials off the hookOn Thursday, Sindh Chief Minister Murad Ali Shah ordered the removal of senior officials, including Waseem Shamshad, who served as both Sindh Building Control Authority (SBCA) director general and local government secretary, and the suspension of 16 SBCA officers following a deadly building….
On the advice of the home minister, he directed the immediate removal of SSP East Zubair Sheikh over alleged negligence.Turning to those directly linked to the construction, the chief minister directed the police to immediately arrest the building owner, Salman Tahir, and the builder, Zeeshan.He also instructed the chief secretary to include the building’s architect and structural engineer in the investigation to establish whether the construction had complied with approved….
However, six extra floors were allegedly added, turning it into a residential complex comprising more than 20 flats.
The building had reached seven storeys despite the approved plan, with construction of a seventh floor reportedly under way for a penthouse when it collapsed.A local resident told The Express Tribune that construction of six floors had been completed on Tuesday and work had then begun on the seventh.
He also said boring work was underway to extract underground water and that residents had experienced intense ground vibrations.The collapse prompted a wider crackdown on suspected illegal construction in the neighbourhood.
The Sindh Building Control Authority sealed 12 other under-construction buildings in Administrative Society and began examining their ownership records, construction documents and approvals to determine whether they complied with building regulations.
Death toll in Karachi building collapse rises to 15 as two more bodies recovered Muhammad Shahmir Khan | Updated 16 minutes ago | Victim identified as Muhammad Mufeed, identification process for other recovered body underway, Rescue 1122 says.

Pakistan · World · Independent Digital Newsroom